Budgeting Variance

A budgeting variance is the difference between a budgeted figure and the actual result for revenue or costs, labelled favourable or unfavourable, and analysed to explain performance, correct course and improve future forecasts.

What is a budgeting variance?

A budget variance measures how far actual results moved from the budget:

Variance = Actual − Budget

  • Favourable (F): revenue higher than budget, or costs lower than budget.
  • Unfavourable or adverse (U/A): revenue lower than budget, or costs higher than budget.

It is often shown as an amount and a percentage of budget.

Types of variances

  • Revenue variance: split into a price variance (selling at a different price) and a volume variance (selling a different quantity).
  • Cost variance: split into price (paying more or less per unit) and usage or efficiency (using more or fewer units).
  • Fixed overhead variance: spending above or below the fixed cost budget.

Example

A business budgeted marketing spend of $5,000 and actually spent $6,200. The variance is $1,200 unfavourable (24%). Sales were budgeted at $50,000 and came in at $56,000, a $6,000 favourable variance. The extra marketing may have paid for itself.

How to run a variance analysis

  1. Compare budget and actual line by line each month.
  2. Focus on variances above a set threshold, such as 10% or a fixed amount.
  3. Find the cause: timing, price, volume, one-off events or errors.
  4. Decide what to do: act, accept or update the forecast.

A flexible budget, adjusted to actual activity levels, gives a fairer comparison for variable costs.

Why it matters

Variances turn a budget from a static document into a management tool. They show where the business is beating or missing plan and why.